The heir to the throne was due 60 days from now and the first-time father had a serious construction project on his hands converting his man cave into a nursery
The seven activities, their normal and expedited times (in days) and costs appear in the table. Just to be on the safe side, he decided to bring the project in at 53 days in case the delivery was a week early. Tell him what the least expensive 53-day project is; which activities should be reduced in duration, by how many days, and at the total cost, so he can roll up the sleeves on his "World's Greatest Dad" sweatshirt, and get to work.
Activity Normal time Crash time Normal Cost Crash Cost Predecessor
A 5 3 500 1100
B 18 15 900 2300 A
C 12 9 2500 3000 A
D 9 7 500 650 B
E 15 12 3000 5000 B
F 12 10 4000 5000 C, D
G 20 15 3600 4800 E, F
The project before any expediting takes 64 days. The activities that should be expedited are D, for 2 days at $75/day; G for 5 days at $240/days; and A for 2 days at $300/day, and B for 2 days at $466.67/day. The total cost to expedite is $2,883.33 in addition to the normal cost of $15,000, for a total tab of $17,883.33 plus a lifetime of disappointment and shame.
You might also like to view...
The Likert scale has several advantages. Which of the following is not an advantage?
A) It does not require a pretest of the adjectives or phrases to ensure bipolarity. B) Respondents readily understand how to use the scale. C) It is suitable for mail, telephone, or personal interviews. D) It is easy to construct and administer.
Outline the steps in developing effective marketing communications
What will be an ideal response?