A PERT chart:

A) portrays a project as a network diagram consisting of numbered nodes that represent tasks.
B) is used to evaluate project risk and time.
C) displays a horizontal bar for each project task.
D) tracks progress of, and modifications to, project tasks.
E) is used to evaluate project costs and benefits.

A