Identify, in order, the six steps basic to both PERT and CPM

What will be an ideal response?

1. Define the project and prepare the WBS.
2. Develop the relationships among the activities.
3. Draw the network connecting all of the activities.
4. Assign the time and/or cost estimates to each activity.
5. Compute the critical path–the longest time path through the network.
6. Use the network to help plan, schedule, monitor, and control the project.

Business

You might also like to view...

Surplus lines brokers are authorized to place coverage with nonadmitted insurers.

a. true b. false

Business

If a manager uses positive or negative reinforcement when an employee completes a task, the manager is trying to

a. strengthen the behaviour of completing the task. b. weaken the behaviour of completing the task. c. strengthen the behaviour of completing the task with positive reinforcement and weaken the behaviour of completing the task with negative reinforcement. d. weaken the behaviour of completing the task with positive reinforcement and strengthen the behaviour of completing the task with negative reinforcement.. e. intermittently strengthen the behaviour by using positive reinforcement and then negative reinforcement.

Business