The value of work completed for an activity is determined by which of the following?
A) budgeted cost - actual cost
B) actual cost divided by budgeted cost
C) percentage of work completed multiplied by actual activity cost
D) percentage of work completed multiplied by budgeted activity cost
E) activity difference divided by budgeted cost
D
You might also like to view...
Researching an organization before an interview
A) will save time during the interview, as the employer won't have to ask as many questions. B) is a bad idea, as it will limit the organizations opportunity to sell the organization. C) will show you understand the importance of investigation and analysis. D) allows you to tell the interviewer how much you know that they may not. E) leads to fewer questions about you, and more questions about the goals of the organization.
Which of the following is a reason why Great Britain and the United States could finance their deficits by borrowing private money since the early 1970s?
A. Rapid development of global capital markets B. Shortage of International Monetary Fund grants available for disbursal C. High interest rate charged by the International Monetary Fund D. Establishment of currency boards in these countries E. Decline of the Bretton Woods system