Which of the following statements about project crashing is false?

A) The crash cost is greater than or equal to the normal cost of an activity.
B) The crash time is less than or equal to the normal time to complete an activity.
C) Reducing the time of an activity on the critical path automatically reduces total project duration.
D) It may not be possible to crash a particular activity.
E) Crashing may not lead to an overall reduction in costs for the project.

C

Business

You might also like to view...

Objective and subjective product criteria are developed during the ________ stage of the purchase decision process so that the decision can be made in the next stage.

A. prepurchase behavior B. problem recognition C. implementation D. alternative evaluation

Business

Which of the following practices can help businesses gain a cost competitive advantage?

a. Innovating simplified production techniques b. Using expensive raw materials c. Customizing products with extra frills d. Manufacturing products in smaller quantities

Business