What is the average lateness of these seven jobs if they are scheduled using the earliest due date criterion?

Job Process Time Due Date
Job 1 15 23
Job 2 7 15
Job 3 12 34
Job 4 8 16
Job 5 11 27
Job 6 10 19
Job 7 13 28

A) 19.2
B) 18.7
C) 17.8
D) 16.5

Answer: C