Use this activity precedence table to create a resource loading profile. Activity lengths are given in days and an 8-hour day is assumed

Activity Time Predecessor
A 2
B 3 A
C 6 B
D 5 A
E 3 C
F 2 D
G 2 E,F

What will be an ideal response?

The loading chart is as follows:

Task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A 8 8
B 8 8 8
C 8 8 8 8 8 8
D 8 8 8 8 8
E 8 8 8
F 8 8
G 8 8
Total 16 16 16 16 16 16 16 16 16 8 8 8 8 8 8 8

The loading profile shows the number of hours required for each of the 14 days of the project.

Business

You might also like to view...

Which of the following describes the projective technique in which respondents are provided with part of a story and required to give the conclusion in their own words?

A) word association B) sentence completion C) story completion D) role playing E) evaluation technique

Business

Marketing prescriptive models can utilize RFM data to maximize future valuation of marketing campaigns under limited campaign resources

a. True b. False

Business