A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities H and I can be represented by a hammock activity
What are the early start and late finish times associated with this hammock activity?
Time Predecessor
A 7
B 8 A
C 13 B
D 8 C
E 7 A
F 6 E
G 6 A
H 11 G
I 12 H
J 14 D, F, I
A) 13, 36
B) 13, 24
C) 24, 36
D) 7, 36
A
You might also like to view...
Haddock Partiers was once the premier supplier of party-equipment for a range of occasions in
the Dallas area. However, post-recession Haddock has seen a slump in sales and is planning to slash the profit margins on most of its products to the bare minimum so that it can tide over the difficult market situation. Which of the following pricing objectives would best serve Haddock Partiers? A) profit maximization pricing objective B) survival pricing objective C) market share maximization pricing objective D) product-quality leadership maximization objective
Sometimes the court awards a very small sum (usually $1 ) in ________ damages to a party that is injured by a breach of contract but cannot show real damages
In these cases, the court generally enables the injured party to recover court costs, though not attorney's fees. A) liquidated B) nominal C) punitive D) compensatory