Which statement on MRP explosion is BEST?
A) It calculates the total number of subassemblies, components, and raw materials needed for each parent item.
B) It calculates the total number of raw materials to be purchased from all suppliers.
C) It calculates the total number of parts to be produced for each parent item.
D) It calculates the total number of parts needed to be produced less the number of parts on hand for each parent item.
A
You might also like to view...
Which company most likely has a philosophy that elevates customer service to the highest level?
A. a company that would rather have customers go to the customer service department than let salespeople handle complaints B. a company that institutes a no-hassle, no time-limit return policy C. a company that allows items purchased online to be returned within 10 days D. a company whose website shows the product offering, but doesn't allow customers to purchase items online E. a company that allows customers to request a shipping label to return a product
With suf?cient preparation and practice, nervousness before public speaking can be reduced by as much as
A) 100% B) 10% C) 50% D) 75%