A brake system installer in an auto factory has an actual average time of 10 minutes on her task. The performance rating of the worker timed was estimated at 110%. Practice in this department is to allow 9% for allowances
a. Find the normal time for the operation.
b. Compute the standard time for the operation.
a. Normal time = (10 minutes)(1.10 ) = 11 minutes
b. Standard time = = = 12.09 minutes