A brake system installer in an auto factory has an actual average time of 10 minutes on her task. The performance rating of the worker timed was estimated at 110%. Practice in this department is to allow 9% for allowances

a. Find the normal time for the operation.
b. Compute the standard time for the operation.

a. Normal time = (10 minutes)(1.10 ) = 11 minutes

b. Standard time = = = 12.09 minutes

Business

You might also like to view...

When a customer says, "I would rather not tie up my money in a large order," the resistance most likely falls into which category?

A) time B) product C) price D) source E) process

Business

If computing a causal linear regression model of Y = a + bX and the resultant r2 is very near zero, then one would be able to conclude that

A) Y = a + bX is a good forecasting method. B) Y = a + bX is not a good forecasting method. C) a multiple linear regression model is a good forecasting method for the data. D) a multiple linear regression model is not a good forecasting method for the data. E) None of the above

Business