Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a variance of 64. There is a .90 probability that the project will be completed before approximately day:

A) 98.
B) 108.
C) 109.
D) 115.
E) 118.

E

Business

You might also like to view...

Which of the following approaches to resolving conflicts is most likely to result in quick solutions, but often leads to relational conflicts?

A) Compromise B) Avoid confrontation C) Collaborate to find the best solution D) Accommodate E) Compete to win

Business

The Labor-Management Relations Act is also known as the Walsh-Healey Act

Indicate whether the statement is true or false

Business