For cost control purposes, actual costs should be compared to
a. a static budget.
b. a flexible budget.
c. actual costs for the prior budget.
d. the original budget.
b
You might also like to view...
The goal of the Health Reform Act is to increase the number of persons who have health care insurance in the United States
Indicate whether the statement is true or false
Your next project consists of 10 consecutive 8-day activities, each estimated by a different worker in your organization. Note that the estimators have not yet added any buffer to the 8-day figure
Your organizational culture dictates that you add your own safety margin of 30% into your estimates. The new project manager has just completed an excellent course in project management offered at the local university. When the first project meeting begins, he dazzles you with his wit and sophistication. You are considerably less charmed when he reveals that he has an exciting new technique for managing projects. He adheres to critical chain project management ideas and plans to create an overall project safety buffer after trimming the safety buffers from each of the 10 activities. How much closer has the project deadline moved? A) 12 days B) 6 days C) 18 days D) 9 days