Your next project consists of 10 consecutive 8-day activities, each estimated by a different worker in your organization. Note that the estimators have not yet added any buffer to the 8-day figure

Your organizational culture dictates that you add your own safety margin of 30% into your estimates. The new project manager has just completed an excellent course in project management offered at the local university. When the first project meeting begins, he dazzles you with his wit and sophistication. You are considerably less charmed when he reveals that he has an exciting new technique for managing projects. He adheres to critical chain project management ideas and plans to create an overall project safety buffer after trimming the safety buffers from each of the 10 activities. How much closer has the project deadline moved?
A) 12 days
B) 6 days
C) 18 days
D) 9 days

A

Business

You might also like to view...

In modern organizations, _____ are the most important resource.

Fill in the blank(s) with the appropriate word(s).

Business

Direct foreign investment and foreign portfolio investment both can be beneficial to an FI because of imperfectly correlated returns with domestic investments.

a. true b. false

Business