The proejct manager and the team have developed response plans for the identified risks. A senior manager has asked for the amount of risk reserves needed for the project. What is the FIRST thing the project maanger should do?

A. Prioritize the list of risks.
B. Create the overall risk rating for the project.
C. Analyse secondary risks.
D. Create the risk reserves.

Answer: C. Analyse secondary risks.

Business

You might also like to view...

Your bank, First Bank, charges you $1.50 every time you use an ATM that is not owned by them. Unfortunately, there is no First Bank ATM near your school

There is a Second Bank ATM in the Student Center, which you use several times a week to withdraw $10 at a time for lunch, video games, etc. What is the best piece of advice regarding these transactions? A) They will make it hard to balance your account since these transactions won't show up on your monthly statements. B) They're OK as long as you enter the transactions in your check register. C) Avoid them since you are effectively paying 15% interest to access your cash. D) Make sure you have overdraft protection on your account.

Business

Journaling your anger and then sharing the writing with those you are angry with is an effective strategy for achieving emotional control in your life

Indicate whether the statement is true or false

Business