Refer to the scenario above. The manager assigns tasks to workstations and breaks ties using a longest operation heuristic
That is, if two or three tasks could be assigned to a given station, the manager assigns the longest task first and then fills in the remaining time at the workstation as completely as possible. Using this approach, what task(s) would be assigned at the fourth station?
A) N, P
B) M
C) N, O
D) O, P
Answer: B
You might also like to view...
The NPV of an investment made today is $10,000. If postponed for one year, the NPV at that time will increase by $1,000. Which of the following is correct if the opportunity cost of the investment is 12 percent?
A) postpone; the NPV will be larger. B) postpone; the NPV increases by a positive amount. C) invest now; always accept positive NPV projects. D) invest now; NPV does not grow at a sufficient rate.
Public relations practitioners should maintain a healthy knowledge of current events MOSTLY because ________
A) they may need to put that knowledge to work for a client or employer B) it makes for a much more interesting professional life C) it demonstrates how management can shape policy D) they may need to "spin" the news on behalf of their employer