Describe the three different categories of risk events that occur during the control risk process, and some of the risk resolution strategies that might be used for each

Key concepts to be covered in the response could include, but are not limited to:

Control risks is the process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout the project.

There are a number of good practices that a project manager can employ depending on whether they have full, partial, or no control over risk events:

Risks fully within project control - Resolution strategies include closely monitoring and controlling activities in progress, documenting all change requests, and researching challenging issues early.

Risks partially within project control - Establish limits to customer expectations; use honesty in managing client expectations, and carefully escalate problems.

Risks outside project control - Actively monitor project environment; understand willingness or reluctance of stakeholders to agree to changes.

Business

You might also like to view...

Under Landrum-Griffin, local unions must elect officers at least once every three years exclusively by secret ballot

Indicate whether the statement is true or false

Business

Unless special arrangements have been made, a meeting between a subordinate and a manager is expected to be held in the

A) conference room. B) manager's office. C) subordinate's office. D) cafeteria.

Business