What would be the estimated time for completion if time estimates for installation are as follows? optimistic = 1 week; pessimistic = 1 week; realistic = 1 week
A) 5 weeks
B) 12 weeks
C) 6 weeks
D) 3 weeks
E) 1 week
E
Explanation: E) You would use realistic time.