Refer to the diagram below, where the numbers next to the arrows refer to the number of days required for completion of the corresponding activity. What is the critical path?
A) A-B-D-F
B) A-C-E-F
C) A-B-D-E-F
D) A-C-B-D-F
E) A-C-B-D-E-F
Answer: A