The estimated duration of an activity is how long it will take to complete each activity based on
a. the estimate of resources to be applied to the activity.
b. the estimate of time for one person to complete the activity.
c. the amount of time listed in the lessons learned from other projects.
d. the amount of funds for that activity.
a