The _________ is a company's internal Web site, containing information for employee access only.
A. extranet
B. intranet
C. corpnet
D. govnet
Ans: B. intranet
You might also like to view...
A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks
What is the lowest total cost for completing this project? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 $12,000 5 $22,000 B A 12 $18,000 9 $32,000 C A 15 $22,000 9 $62,000 D B 3 $9,000 2 $18,000 E C 9 $15,000 5 $35,000 F E 7 $5,000 5 $8,000 G D 8 $13,000 6 $23,000 H A 12 $20,000 8 $32,000 J H 6 $45,000 4 $56,000 A) $172,000 B) $184,000 C) $187,000 D) $192,500
The document that shows the component parts and the number of parts needed to make one of an
assembly or subassembly is called: A) a material requirements plan. B) a bill of material. C) a route sheet. D) a material requisition. E) none of the above