A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks

What is the lowest total cost for completing this project?

Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost
A -- 8 $12,000 5 $22,000
B A 12 $18,000 9 $32,000
C A 15 $22,000 9 $62,000
D B 3 $9,000 2 $18,000
E C 9 $15,000 5 $35,000
F E 7 $5,000 5 $8,000
G D 8 $13,000 6 $23,000
H A 12 $20,000 8 $32,000
J H 6 $45,000 4 $56,000
A) $172,000
B) $184,000
C) $187,000
D) $192,500

B

Business

You might also like to view...

What listening style is described as not being responsible for listening?

What will be an ideal response?

Business

To which of the following rights is a shareholder of a public corporation entitled?

A. The right to have annual dividends declared and paid. B. The right to vote for the election of officers. C. The right to a reasonable inspection of corporate records. D. The right to have the corporation issue a new class of stock.

Business