What are the earliest activity start time and latest activity start time, and how are they computed?

What will be an ideal response?

The earliest start time (ES) is the earliest time at which an activity may start and still satisfy all precedence requirements. ES = Max{EF of all immediate predecessors}. The latest start time is the latest time at which an activity may start and still satisfy both precedence requirements and the overall project completion time. LS = LF - Activity time.

Business

You might also like to view...

In the opening paragraph of an application letter, it is vital to

A) indicate what you are looking for in a dream job, and how the open position matches your goals. B) identify the position you are applying for and your salary range. C) explain how you can help the company meets its needs. D) let the employer know highlights from your résumé. E) make sure the employer understands that you need a response within 24 hours.

Business

After creating a message strategy statement, the advertiser must develop a compelling ________ that will bring the message strategy to life in a distinctive and memorable way

A) creative concept B) customer strategy C) customer benefit D) execution style E) media vehicle

Business