Early start and early finish times for all activities appear in the table.

Task Early Start Early Finish
A 0 1
B 1 8
C 1 6
D 8 9
E 8 16
F 9 18
G 9 23
H 23 31
K 23 26
L 31 37

Business

You might also like to view...

Which of the following is TRUE regarding a matrix-management organization?

A) It is a low-cost form of organization. B) It often creates conflicts regarding authority and responsibility for marketing activities. C) It hampers the flow of information among marketing personnel. D) It promotes the matrix concept throughout the company. E) It is best suited to companies that offer a small range of products to niche markets.