Tim usually exhibits a 90% learning rate for the mechanical tasks he undertakes. His next big project, the fence along the street, will require 24 iterations of the fencepost task

If he has 40 hours available to work on the project, how fast must he perform the first iteration in order to finish all 24 within his allotted time? Refer to the copy of Table I.1 appended to this exam.

The first unit must be finished in 2.34 hours in order to get all 24 units done in 40 hours.