Consider the project that is neatly summarized in this table

What are the top two priority activities when using the smallest duration leveling heuristic?

Activity Duration Predecessors Workers Required
A 2 -- 3
B 4 A 4
C 6 A 2
D 7 B 5
E 9 C, D, E 2
A) B and C
B) A and B
C) C and E
D) A and E

B