What is the total project budget for design in this time-phased budget?

Activity July August September October November
RFP 34,721
Analysis 11,049 33,655 34,388
Design 33,718 34,474 26,759 36,328
Coding 7,713 34,905 40,244
Testing 40,916 896
Training 20,958 9,327
Roll-Out 8,186
A) $131,279
B) $155,330
C) $124,688
D) $146,983

A