What is the average lateness of these seven jobs if they are scheduled using the critical ratio criterion?
Job Process Time Due Date Job 1 15 23 Job 2 7 15 Job 3 12 34 Job 4 8 16 Job 5 11 27 Job 6 10 19 Job 7 13 28 A) 24.3 B) 21.7 C) 22.5 D) 23.4