What is the average lateness of these seven jobs if they are scheduled using the critical ratio criterion?
Job Process Time Due Date
Job 1 15 23
Job 2 7 15
Job 3 12 34
Job 4 8 16
Job 5 11 27
Job 6 10 19
Job 7 13 28
A) 24.3
B) 21.7
C) 22.5
D) 23.4
Answer: B