Consider the timing of the profits of the following certain investment projects:

Profit
L S
Year 1 $ 0 $ 3000
Year 2 $ 3000 $ 0

A) Project S is preferred to Project L.
B) Project L is preferred to Project S.
C) Projects S and L are equally desirable.
D) A goal of profit maximization would favor Project S only.

Answer: A

Business

You might also like to view...

In the context of the Critical Path Method (CPM), the slack time (ST) for an activity is computed as:

A) the latest start (LS) time minus the earliest finish (EF) time. B) the latest finish (LF) time minus the earliest start (ES) time. C) the latest start (LS) time minus the earliest start (ES) time. D) the earliest finish (EF) time minus the latest start (LS) time.

Business

The Responsible Management in Action case about Samsung

a. illustrated how the company emphasizes sustainability performance throughout the training and development process b. stated that it has doubled the growth of its Human Resources Development Center (HRDC). c. showed it was the first company to develop a responsible Supplier Code of Conduct. d. specified how management sharpened its HRDC solely on the "sustainability expertise" of future-oriented employees.