In the context of the Critical Path Method (CPM), the slack time (ST) for an activity is computed as:
A) the latest start (LS) time minus the earliest finish (EF) time.
B) the latest finish (LF) time minus the earliest start (ES) time.
C) the latest start (LS) time minus the earliest start (ES) time.
D) the earliest finish (EF) time minus the latest start (LS) time.
C
You might also like to view...
Whether or not key publics were missed in the original determination of stakeholder groups relates to which phase of research?
A. Outputs D. Implementation B. Outcomes E. Impact C. Preparation
In which of the following cases would a fiduciary duty be breached?
A) A stockbroker advises a client to buy shares in a company in which he is a substantial shareholder without disclosing the fact of his preexisting shareholding to the client B) A director of a company buys property from the company after misrepresenting its true value to the other members of the board of directors C) A real estate agent who has been authorized to search for property buys a property and sells it back to his client for three times the value D) A stockbroker advising an elderly woman on investing money after her husband died and she has no investing experience and he has her put it into a new startup he owns E) All of the above