A production line is to be designed to make 500 El-More dolls per day. Each doll requires 11 activities totaling 16 minutes of work. The factory operates 750 minutes per day. What is the required cycle time for this assembly line?
A) 0.5 minutes
B) 1.5 minutes
C) 2 minutes
D) 5,500 minutes
E) 4.26 minutes
B