Pert
A) assumes that we do not know ahead of time what activities must be completed.
B) assumes that activity time estimates follow the normal probability distribution.
C) is a network technique that uses three time estimates for each activity in a project.
D) is a deterministic network technique that allows for project crashing.
E) None of the above
C
Business
You might also like to view...
At the age of 34, Ben purchased a whole life policy with a guaranteed insurability option. How many opportunities will he have to purchase additional life insurance in the future?
A) 5 B) 4 C) 2 D) 3"
Business
Michealson suggests that researchers have a moral obligation to make workplaces better for employees.
a. true b. false
Business