Pert

A) assumes that we do not know ahead of time what activities must be completed.
B) assumes that activity time estimates follow the normal probability distribution.
C) is a network technique that uses three time estimates for each activity in a project.
D) is a deterministic network technique that allows for project crashing.
E) None of the above

C