What does a project manager do during the project execution phase? List the steps in the project execution phase

What will be an ideal response?

As project manager, you oversee the execution of the baseline plan. This means that you initiate the execution of project activities, acquire and assign resources, orient and train new team members, keep the project on schedule, and ensure the quality of project deliverables. The steps in the project execution phase include:
1. Executing the Baseline Project Plan
2. Monitoring Project Progress against the Baseline Project Plan
3. Managing Changes to the Baseline Project Plan
4. Maintaining the Project Workbook
5. Communicating the Project Status.