A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before which day (rounded to nearest day)?
A) 98
B) 112
C) 120
D) 124
E) 220
B
Business
You might also like to view...
Regarding alternate site data-processing facilities, which of the following best practices is MOST important?
A. The facility is not clearly identified as belonging to the company. B. The facility is clearly identified as belonging to the company. C. Primary-site recovery teams can reach the facility within an hour to ensure minimal business impact from the disruptive event. D. The facility does not provide any external windows.