Use the project described in the table to determine the total resources required for this project if a worker is expected to devote half-time (four hours per day) to this project
Activity Duration Predecessor
A 5 days --
B 4 days A
C 5 days A
D 6 days B
E 6 days C, D
F 6 days E
A) 36 hours
B) 40 hours
C) 64 hours
D) 128 hours
D
You might also like to view...
A company begins the year with some debt. During the year the company makes a profit and retains some of its earnings, adding to its cash. It otherwise takes no action to alter its balance sheet. What is its new leverage ratio compared to the start of the year?
a) higher b) lower c) the same d) none of the above
The purpose of sales training needs assessment is to compare the specific performance-related skills, attitudes, perceptions, and behaviors required for salesforce success to the
a. salesforce rating results of a customer survey. b. performance test results of each salesperson. c. job analysis of each sales position. d. state of readiness of the salesforce. e. personal observations of various salespeople recorded by sales managers.