The net present value (NPV) for project alpha is closest to ________
Consider the following two projects:
Project Year 0
C/F Year 1
C/F Year 2
C/F Year 3
C/F Year 4
C/F Year 5
C/F Year 6
C/F Year 7
C/F Discount
Rate
Alpha -79 20 25 30 35 40 N/A N/A 12%
Beta -80 25 25 25 25 25 25 25 13%
A) $31.35
B) $25.08
C) $37.62
D) $21.32
Answer: B