Negative slack indicates a lack of slack over the entire project and the amount of time
a. an activity must be accelerated to complete the project by the required completion time.
b. an activity must be delayed to complete the project by the required completion time.
c. each activity on the critical must be accelerated to complete the project by the required completion time.
d. all activities in the project must be accelerated to complete the project by the required completion time.
a
You might also like to view...
Which of the following is NOT true of the range?
A) It identifies the distance between the lowest value and the highest value in a set of numbers. B) It identifies the maximum and the minimum in a set of numbers, and you can do a quick mental calculation to see how many units are in between. C) The range tells you how often the maximum and minimum occurred. D) It provides some information on the variability by indicating how far apart the extremes are found. E) If you find that the range is very narrow, you know that the average is typical of many respondents.
Briefly describe the steps that make up the selling process
What will be an ideal response?