A seven activity project has the activity durations (in weeks) and costs shown in the table. The project manager has an overall budget of $20,000, what is the fastest completion time possible?
Activity
Predecessor Normal Duration
Normal Cost Crash Duration
Crash Cost
A -- 7 $2000 5 $3000
B -- 8 $1500 6 $2000
C A 12 $2500 10 $2900
D B 13 $3000 10 $4200
E B 15 $4000 12 $5500
F C, E 10 $3200 8 $4000
G D 7 $1800 6 $2200
A) 29 weeks
B) 28 weeks
C) 27 weeks
D) 26 weeks
Answer: B
You might also like to view...
Nobody seems to know what their role is and what they are supposed to do in one of your divisions. Two people have applied for the job as manager of this struggling division
They are equal in experience and knowledge; however, Robert has been classified as external and Susan has been classified as an internal. Who should you hire? A) You should hire Susan. B) You should hire Robert. C) You should continue your job search outside the division, as neither Susan nor Robert are qualified for the job. D) These classifications do not help in selecting the right candidate for this job.
Persuasive techniques in the digital age involve the use of flattery, empathy, nonverbal cues, and likability appeals
Indicate whether the statement is true or false