Which activity should be crashed to reduce the project completion by 2 days?
A) Crash activity B by 1 day and Activity C by 1 day.
B) Crash activity E by 2 days.
C) Crash activity C by 1 day and activity E by 1 day.
D) Crash activity B by 2 days.
Answer: C