To complete the first setup on a new machine took an employee 300 minutes. Using an 85% cumulative average-time learning curve indicates that the second setup on the new machine is expected to take ________
A) 127.50 minutes
B) 210 minutes
C) 277.50 minutes
D) 255 minutes
Answer: B
You might also like to view...
A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table. Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks
What day does activity K start under a leveled project with the four worker limitation? Activity Activity time Workers Needed Predecessor A 10 1 B 4 2 C 7 3 A D 4 1 A E 8 2 B F 9 3 C,E G 13 1 D H 14 2 E,G J 13 3 F K 10 1 H, J L 5 2 K A) Day 56 B) Day 57 C) Day 58 D) Day 59
Forward buying results in
A) a stabilized buying pattern. B) small orders during the promotion period followed by very small orders after that. C) small orders during the promotion period followed by large orders after that. D) large orders during the promotion period followed by very small orders after that.