A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table. Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks

What day does activity K start under a leveled project with the four worker limitation?

Activity Activity time Workers Needed Predecessor
A 10 1
B 4 2
C 7 3 A
D 4 1 A
E 8 2 B
F 9 3 C,E
G 13 1 D
H 14 2 E,G
J 13 3 F
K 10 1 H, J
L 5 2 K
A) Day 56
B) Day 57
C) Day 58
D) Day 59

A

Business

You might also like to view...

Cybil is insured under a key-person life insurance policy owned by Delta Corporation and then quits her job. Which of the following statements is NOT correct?

A) Cybil can convert the policy to an individual policy. B) Delta can surrender the policy for cash. C) Delta can keep the policy in force. D) Delta can assign the policy."

Business

A trader creates a long butterfly spread from options with strike prices $60, $65, and $70 by trading a total of 400 options. The options are worth $11, $14, and $18

What is the maximum net gain (after the cost of the options is taken into account)? A. $100 B. $200 C. $300 D. $400

Business