If using Monte Carlo simulation, what is a typical number of iterations employed in the model?
A) 1
B) 10
C) 1,000
D) 1,000,000
C
Business
You might also like to view...
A project consisting of six activities is shown in the table
If the project manager decides to operate on an early start schedule, which of these days has the highest resource requirements? Activity Duration (days) Activity Cost Predecessor K 10 140 L 8 64 K, M M 12 96 N 6 120 M P 14 168 L Q 12 144 N A) Day 5 B) Day 10 C) Day 15 D) Day 20