A project consisting of six activities is shown in the table
If the project manager decides to operate on an early start schedule, which of these days has the highest resource requirements?
Activity Duration (days) Activity Cost Predecessor
K 10 140
L 8 64 K, M
M 12 96
N 6 120 M
P 14 168 L
Q 12 144 N
A) Day 5
B) Day 10
C) Day 15
D) Day 20
C
You might also like to view...
Which of the following is one of the main purposes of FTZs?
A) discouraging companies to locate in the host country B) forcing countries to pay extra duties C) discouraging companies from using JIT D) allowing countries to defer duties
A forward contract to deliver British pounds for U.S. dollars could be described either as ________ or ________
A) buying dollars forward; buying pounds forward B) selling pounds forward; selling dollars forward C) selling pounds forward; buying dollars forward D) selling dollars forward; buying pounds forward