Consider a project that has an expected completion time of 60 weeks and a standard deviation of five weeks. What is the probability that the project is finished in 70 weeks or fewer? (Round to two decimals.)

A) 0.98
B) 0.48
C) 0.50
D) 0.02
E) 0.63

A