What is the objective of critical path analysis?
What will be an ideal response?
Critical path analysis determines the longest path through a network of activities. This longest path is the key to making the schedule that provides for completing all activities in the shortest time. Critical path analysis identifies those activities critical to timely completion of all activities so they can receive management focus.
You might also like to view...
To prepare a statement of cash flows (indirect method), which of the following items should be added back to net income to derive "cash flow from operating activities?"
A. Depreciation expense. B. Increase in accounts receivable. C. Loss on a sale of equipment. D. Two of the above are correct.
In the context of medical malpractice, what is a "never event"?
A) A medical condition that despite the best screening and technology cannot be detected. B) A pandemic that quickly spreads and infects many people. C) A medical error that should never occur. D) An event for which doctors and medical facilities cannot be held legally responsible.