Which of the following is NOT a limitation of PERT?

A) Project activities have to be clearly defined, independent, and stable in their relationships.
B) Precedence relationships must be specified and networked together.
C) Only one time estimate can be used for each activity.
D) Time estimates tend to be subjective and are subject to fudging by managers.
E) There is the inherent danger of placing too much emphasis on the critical path.

C

Business

You might also like to view...

Federal trademark provides protection for 20 years and may be renewed for additional 20- year periods.

a. true b. false

Business

Aric purchased a digital camera at a significant discount. Though the camera did not have all of the features he had wanted, he was pleased with the reduced price

Aric thought the photos he took with the camera were of a high quality, but he was disappointed that the camera did not have a larger memory and that its batteries needed to be replaced so frequently. Aric is best described as a ________ customer. A) loyal B) delighted C) defecting D) product champion E) switchable

Business