It costs $75 per day for each day that a construction crew is on site. The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity

Use this information to determine the lowest cost for this project. All times given are in days.

Activity Normal Time Minimum Time Crash Cost ($/day) Predecessor
A 10 6 $70 --
B 6 3 $40 --
C 2 2 -- B
D 4 2 $60 C
E 6 4 $80 A
F 8 5 $90 D, E
A) $1,720
B) $1,750
C) $1,780
D) $1,810

C

Business

You might also like to view...

Olive Inc, a chain of retail outlets, is converting its existing billing systems to a more robustonline tool. In this process, the organization runs both the old and the new systems to comparetheir performances

In this case, the company is implementing the new system using ________installation.A) parallel B) pilot C) plunge D) phased

Business

Kyle Winston borrowed $4,00 . for 90 days. At the due date, he paid $75 interest and repaid all of the principal. What was the ordinary simple interest rate (360-day year) that was charged on the loan? (To nearest 1/10 of a percent.)

Business