Which of the following refers to the time in which an activity can be completed without delaying the project?
A) Latest expected completion time
B) Earliest expected completion time
C) Delay time
D) End time
E) Critical time
A
Explanation: A) The latest expected completion time tells us what the very latest time is for an activity to be completed before the project is delayed. This applies to activities along the critical path.
You might also like to view...
Which of the following is most likely true about shoppers who prefer to shop at lifestyle centers?
A) They prefer inexpensive, thrifty atmospheres. B) They value an aesthetically pleasing shopping environment. C) They prefer out-of-the-way locations. D) They rarely dine out. E) They are motivated by deals on last year's merchandise.
The _____ section of a case brief includes a listing of the laws the court relied onin the analysis or reasoning and may include statutes, case law, articlesor amendments from the U.S. Constitution or other primary sources of the law
Fill in the blanks with correct word