Use the Gantt chart and the activity list to determine which resource is needed earliest in this project
Activity Resources Activity Resources
A 5 F 2
B 6 G 3
C 7 H 4
D 1 J 5
E 2 K 1
A) Resource 2
B) Resource 3
C) Resource 1
D) Resource 4
A