A common tool project teams use is a responsibility assignment matrix (RAM). Typically, this chart will depict:
a. the date each activity will begin.
b. the duration of each activity.
c. the roles key members of the team will play on each activity.
d. organizational reporting structure
C
You might also like to view...
The U.S.-style "I'll do whatever it takes to get your business" has proven to be a successful selling approach throughout the world
Indicate whether the statement is true or false
This excerpt comes from an article titled "Eagle Eyes High-Coupon Callable Corporates" in the January 20, 1992, issue of BondWeek, p
7: "If the bond market rallies further, Eagle Asset Management may take profits, trading $8 million of seven-to 10-year Treasuries for high-coupon single-A industrials that are callable in two to four years according to Joseph Blanton, Senior V.P. He thinks a further rally is unlikely, however. Eagle has already sold seven-to 10-year Treasuries to buy $25 million of high-coupon, single-A nonbank financial credits. It made the move to cut the duration of its $160 million fixed income portfolio from 3.7 to 2.5 years, substantially lower than the 3.3-year duration of its bogey . . . because it thinks the bond rally has run its course. . . . Blanton said he likes single-A industrials and financials with 9 1/2?10% coupons because these are selling at wide spreads of about 100?150 basis points off Treasuries." What types of active portfolio strategies are being pursued by Eagle Asset Management?